• Student AGRAWAL KUNJ SATYANARAYAN
  • Code PSD20180
  • Faculty Technology
  • Tutor/s Devang Patel,Krunal Mehta
  • TA Jaldeep Kabariya

143
views

The Project involves the analysis and Design of Pre Tensioned PSC U Girder of Span 22m with circular pier & Pile Foundation at Bhuj. Grillage analysis is done in STAAD Pro for analysis of the superstructure. The Superstructure, Substructure and Foundation are all analyzed and designed for all of the required loads on each component of the Bridge as per IRC 6, IRC 112 and IRC 71 for the PSC pretensioned girder for the Superstructure