Ahmedabad Metro Phase-1/Package-2

  • Student Shishir Tiwari
  • Code UC6916
  • Faculty Technology
  • Tutor/s Reshma Shah,Devanshu Pandit,Bhargav Tewar,Paresh Shah,Ganesh Devkar,Abhi Jhaveri,Project Training

114
views

This project tender was awarded to Simplex Infrastructure Pvt. Ltd. under whom I have completed my training. The project includes construction of 8.94 km of elevated viaduct and 6 elevated stations two of which have been outsourced to sub-contractors Vishwa Construction Ltd. and Patel Infrastructure Ltd. The project commenced in November 2019 and is expected to be completed by March 2022.